本文介绍了Burndown报告的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧! 问题描述

嗨!

我已经记录了我的基线并希望在输入实际作品之前看到燃尽报告,如下图所示," ;剩余的累积实际工作量"和"剩余的累积工作"不一样。我错过了的东西,我不明白这一点。

I've recorded my baseline and wanted to see the burndown report before entering the actual works, bu as you can see on the picture below, the "remaining cumulative actual work" and the "remaining cumulative work" are not same. Am i missing something, i don't understand this.

感谢您的帮助。

推荐答案

selcukz -

selcukz --

不,Burndown报告是正确的如果您的资源按计划精确执行计划的工作,剩余的累计工作将向您显示预期结果。您可以看到数字随着时间的推移逐渐减少,直到它在项目结束时以降至0。

Nope, the Burndown report is correct. The Remaining Cumulative Work shows you what to expect if your resources perform the planned work precisely on schedule. You can see the number is decreasing over time, as expected, until it drops to 0 at the end of the project.

剩余的累积实际工作是一个平坦的线从项目的开始到结束。这是因为您尚未输入任何实际工作。当您开始为此项目中的资源输入实际工作时,您将看到行更改。

The Remaining Cumulative Actual Work is a flat line from the beginning to the end of the project. This is because you have NOT entered any Actual Work yet. As you begin entering Actual Work for your resources in this project, you will see the line change.

因此,报告是正确的。您缺少的是几个关键概念。鉴于您对Microsoft Project的新见解,这并不奇怪。好的,我为此鼓掌,是你愿意从这个论坛的用户那里获得宝贵的知识。 :)希望这会有所帮助。

So, the report is correct. What you are missing are a couple of key concepts. Given your newness to Microsoft Project, this is not surprising. The good thing, and I applaud you for this, is that you are willing to gave valuable knowledge from the users in this forum. :) Hope this helps.

更多推荐

Burndown报告

本文发布于:2023-11-23 07:00:17,感谢您对本站的认可!
本文链接:https://www.elefans.com/category/jswz/34/1620533.html
版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。
本文标签:报告   Burndown

发布评论

评论列表 (有 0 条评论)
草根站长

>www.elefans.com

编程频道|电子爱好者 - 技术资讯及电子产品介绍!