我已经记录了我的基线并希望在输入实际作品之前看到燃尽报告,如下图所示," ;剩余的累积实际工作量"和"剩余的累积工作"不一样。我错过了的东西,我不明白这一点。
I've recorded my baseline and wanted to see the burndown report before entering the actual works, bu as you can see on the picture below, the "remaining cumulative actual work" and the "remaining cumulative work" are not same. Am i missing something, i don't understand this.
感谢您的帮助。
推荐答案
selcukz -
selcukz --
不,Burndown报告是正确的如果您的资源按计划精确执行计划的工作,剩余的累计工作将向您显示预期结果。您可以看到数字随着时间的推移逐渐减少,直到它在项目结束时以降至0。
Nope, the Burndown report is correct. The Remaining Cumulative Work shows you what to expect if your resources perform the planned work precisely on schedule. You can see the number is decreasing over time, as expected, until it drops to 0 at the end of the project.
剩余的累积实际工作是一个平坦的线从项目的开始到结束。这是因为您尚未输入任何实际工作。当您开始为此项目中的资源输入实际工作时,您将看到行更改。
The Remaining Cumulative Actual Work is a flat line from the beginning to the end of the project. This is because you have NOT entered any Actual Work yet. As you begin entering Actual Work for your resources in this project, you will see the line change.
因此,报告是正确的。您缺少的是几个关键概念。鉴于您对Microsoft Project的新见解,这并不奇怪。好的,我为此鼓掌,是你愿意从这个论坛的用户那里获得宝贵的知识。 :)希望这会有所帮助。
So, the report is correct. What you are missing are a couple of key concepts. Given your newness to Microsoft Project, this is not surprising. The good thing, and I applaud you for this, is that you are willing to gave valuable knowledge from the users in this forum. :) Hope this helps.