Scrum模板燃烧的理想趋势行为。

编程入门 行业动态 更新时间:2024-10-06 12:29:34
本文介绍了Scrum模板燃烧的理想趋势行为。的处理方法,对大家解决问题具有一定的参考价值,需要的朋友们下面随着小编来一起学习吧! 问题描述

嗨伙计,我是b $ b我对tfs燃尽图(scrum模板)中显示的理想趋势的行为表示怀疑。 我明白了该行以累积的"剩余工作"开始。在冲刺开始时。此外,如果我们添加了另一个任务,那么该线路还会添加剩余的新任务。 据我所知,这条线路永远不应该贬低它的价值,因为它应该反映最初的剩余工作。$ 事情是我们在冲刺的第二天添加了一个新的用户故事。那时我们已经完成了1小时的工作。由于新的用户故事,该行被重新计算,但没有考虑到已完成的小时数。 $ 您是否注意到这种行为?是不是因为它是什么?是我想要添加新用户故事的小时而不重新计算前一个小时的行。 非常感谢!

Hi folks, I've a doubt about the behavior of the ideal trend shown in the tfs burndown graph (scrum template). I've understood that the line starts in the accumulated "remaining work" at the start of the sprint. Also if we added another task the line shoulded add the new task remaining work. As I understand the line should never dicrease its value because it should reflect the initial remaining work. The thing is that we added a new user story the second day of the sprint. At that point we already had finished 1 h of work. The line was recalculted because of the new user story but it didn't take into account the finished hours. Do you note this behavior? Is it as it is supose to be? i'd like the line to add the new user story's hours without recalculating the previous one. Thanks very much in advance!

推荐答案

您好Diego Pandiello,

Hi Diego Pandiello,

我测试你上面说的话。昨天,我创建了三个任务,总共剩下11个小时的工作。今天,我完成了一个1小时的任务。那时剩下的工作仍然是11h。

在我添加剩余5小时工作的任务后,理想的趋势起点仍然工作15,而不是16。

After I add a task with 5 hours remaining work, the ideal trend start point remaining work it 15, not 16.

您可以下载Scrum流程模板文件夹,理想趋势的计算方法是在Scrum中编写 - > Reports - > Sprint Burndown.rdl。

You could download Scrum process template folder, thecalculation method of ideal trend is writein Scrum-->Reports-->Sprint Burndown.rdl.

最好的问候

更多推荐

Scrum模板燃烧的理想趋势行为。

本文发布于:2023-11-23 06:54:06,感谢您对本站的认可!
本文链接:https://www.elefans.com/category/jswz/34/1620513.html
版权声明:本站内容均来自互联网,仅供演示用,请勿用于商业和其他非法用途。如果侵犯了您的权益请与我们联系,我们将在24小时内删除。
本文标签:模板   趋势   理想   Scrum

发布评论

评论列表 (有 0 条评论)
草根站长

>www.elefans.com

编程频道|电子爱好者 - 技术资讯及电子产品介绍!