WSO2 BPS(BPEL) - 截止日期或升级表达式(WSO2 BPS(BPEL) - Deadline or Escalation expression)
嗨,我正在研究WSO2 BPS(BPEL)3.1.0,
@My Scenario
如果任务未在给定时间内完成。
我需要给出最后期限,并升级为高级智者。
我试过工作的例子,但我没有得到任何信息。
我如何使用WSO2 BPS(BPEL)实现这一目标。
Hi I am working on WSO2 BPS(BPEL) 3.1.0,
@My Scenario
if task is not completed within the given time.
I need to give the deadlines,and escalated to superior wise.
I tried working examples, but i didn't get any information.
How can i achieve this using WSO2 BPS(BPEL).
最满意答案
WSO2 BPS提供升级支持。 你能看看BPS 3.2.0提供的ClaimsApprovalTaskWithDeadline.zip样本吗?它基本上是根据截止日期做的通知。
关心南迪卡
Escalation support is available with WSO2 BPS. Can you check out the ClaimsApprovalTaskWithDeadline.zip sample available from BPS 3.2.0 which is basically doing a notification based on a deadline.
Regards Nandika