在附加的甘特图中(抱歉,它没有附加,因为它不允许我附加它,直到"它能够验证我的帐户"。它允许我昨天附上图像,为什么不今天?),我选择更新项目和重新安排未完成的工作在2015年12月2日星期三之后开始,为什么它显示任务15从2015年11月24日开始,即使它的前任任务14完成15年3月12日?对于本图表中的许多其他示例,同样如此?我想要它做的是:
现有图表显示过去未完成的任务(例如任务15)正在完成。这肯定是不对的?我们当然知道任务15最早要到今天才能开始,因为它完成了0%。
我如何才能做到这一点?
谢谢 - 罗文
解决方案
罗文 -
如果无法看到该项目,就很难猜测出了什么问题。继续尝试附上屏幕截图或其他内容来帮助我们。感谢。
In the attached Gantt chart (sorry, it's not attached because it would not allow me to attach it until "it was able to verify my account". It allowed me to attach an image yesterday, why not today?), on which I have selected Update Project and Reschedule Uncompleted Work to start after Wed 2/12/15, why does it show task 15 starting on 24/11/15, even though its predecessor task 14 finishes on 3/12/15? And the same for lots of other examples in this section of chart? What I want it to do is:
The existing diagram shows that uncompleted tasks (such as task 15) are being completed in the past. This surely cannot be right? We surely know that task 15 cannot start until today at the earliest, since it is 0% complete.
How do I get it to do this?
Thanks - Rowan
解决方案Rowan --
Without being able to see the project, it would be difficult to speculate what is wrong. Keep trying to attach a screenshot or something to help us. Thanks.